• It is essential that the first two layers of brickwork, or one layer of blockwork, are laid with special care and that the mortar joints both vertical and horizontal are properly filled, leaving no voids. (1:3 cement, sand mortar is recommended).
  • Building blocks may be used if they are solid and have a minimum crushing streanth of 3.0 N/mm˛.
  • In lintels over 1.500m props must be used at the quarter points until mortarwork has matured.
  • Where a D.P.C. is used it must be placed over the second layer of the blockwork
  • Minimum bearing of 150mm each side, or as directed by the strucural engineer.
TYPE B (145x70mm) Permissible UDL (kN/m) per layer of brickwork. Weight: 36m/ton
Clear Span 600 900 1200 1500 1800 2100 2400 2800 3100
Without Brickwork 10.00 7.24 4.49 3.01 2.15 1.62 1.26 - -
1 Layer of Brickwork 13.61 12.01 9.26 6.50 3.02 2.31 1.81 - -
2 Layers of Brickwork 28.00 18.60 10.26 8.25 5.00 3.30 2.78 1.71 1.44
3 Layers of Brickwork 29.50 27.60 25.00 10.00 6.00 4.66 3.98 2.60 2.19
5 Layers of Brickwork 32.00 31.00 30.00 16.50 13.00 9.15 8.00 5.00 4.75
* Please Note: All lintels are designed in accordance with- BS 5977: Part 1: 1981, BS 5977: Part 2: 1983, BS 8110: Part 1: 1985, BS 8110: Part 2: 1985

Download Spec Sheet as a PDF here.





 Robeslee Concrete, Southbank Road, Kirkintilloch, Glasgow. G66 1UA  info@robeslee.co.uk